Summer Road Repaving Program to Begin in June

Lower Merion Township Commissioners approved a contractor Wednesday.

 

A contractor for Lower Merion Township's summer road repaving program was approved at Wednesday night's Board of Commissioners meeting.

The first of two phases of repaving—about 68,110 square yards of milling—should begin about June 18 and end July 20.

After some questions from commissioners about contributions from Aqua (which contributes money when roads are to be repaved by the township, rather than repaving just a patch of road after work is done), Joseph E. Sucher & Sons, Inc. was unanimously approved to complete the project in two phases for about $199,000 total.

Bryn Mawr-Gladwyne area roads to be repaved during that time include:

Paving Lanes Start to Finish Length (yards) Width
Montgomery Avenue Spring Mill Road intersection 80 88
Roscommon Road Morris Avenue to Mt. Pleasant Road 3,455 28
Foxwood Circle Roscommon Road to cul-de-sac 616 30
Woodgate Lane Roscommon Road to cul-de-sac 373 20
Great Springs Road* Ithan Avenue to cul-de-sac 2,397 24
Hoffman Drive Great Springs Road to cul-de-sac 1,112 28
Victor Lane Hoffman Drive to cul-de-sac 437 28
Great Springs Road Old Gulph Road to cul-de-sac 1,800 24
Millbank Road Old Gulph Road to New Gulph Road 1,435 25
Merion Avenue Lancaster Avenue to newly paved area 360 30
Pennswood Road Fishers Road to New Gulph Road 1,245 27
Fishers Road Rose Lane to Old Gulph Road 1,300 20
Fishers Road Rose Lane to New Gulph Road 2,729 24

(The * denotes contributions from Aqua.)

See a complete list of township roads to be paved here.

A second phase of paving—about 68,200 square yards—will run from about Aug. 13 to Sept. 14.

Related Topics: Aqua Pa, Lower Merion Township, and Road Repaving